Wire

Sign in to baba News

One account across the web, iPhone and Android — your subscription follows it.

or use an email code

Search stories

Type at least two characters. Results come from every newsroom baba reads.

↑↓ to move · ↵ to open · esc to close

Sign in to baba News

Sign in to keep asking. News Plus removes the daily limit.

or use an email code

Ongoing Story· Day 7

Israel to Cap New Data Center Power to 200 Megawatts

5 developments

TheMarkerEconomy

Israel Electricity Authority Faces Developer Battle Over Data Center Power

Translated & summarized from TheMarker by baba

BusinessCharged tone

Hebrew · Sole source

The Israel Electricity Authority is seeking public input on managing the queue for data center power connections, having already imposed high guarantees and power limits. Developers are unhappy with the new restrictions and may pursue legal action. The situation highlights intense demand for data center infrastructure in Israel, with limited capacity available.

The story in 5 lines · by baba

  • Israel Electricity Authority will seek public opinion on data center power connection queue management.
  • Approved restrictions include high guarantees and maximum power per data center project.
  • Developers are expected to challenge the new regulations, potentially through legal means.
  • The changes will impact almost all pending data center connection requests.
  • The data center industry in Israel faces significant demand and limited supply.

The Israel Electricity Authority's plenum is expected to solicit public opinion on managing the queue for connecting data centers to the national power grid. Among the restrictions already approved are high guarantees and a maximum power allocation per project. This change is anticipated to affect nearly all connection requests, and developers may take the Authority to court.

The situation in Israel's data center industry is likened to a crowded supermarket or bus station, where patience is scarce. In this high-stakes environment, a product worth billions of dollars is in demand, with only five out of one hundred applicants expected to receive it. The queue management is fluid, with the possibility of the order changing, while numerous applicants vociferously demand preferential treatment.

TheMarkerOther · Tel Aviv

Sign in to baba News

Sign in to follow newsrooms, topics and people.

or use an email code

EconomyTopic

Sign in to baba News

Sign in to follow newsrooms, topics and people.

or use an email code

Mentioned

Open the Wire