Wire

Sign in to baba News

One account across the web, iPhone and Android — your subscription follows it.

or use an email code

Search stories

Type at least two characters. Results come from every newsroom baba reads.

↑↓ to move · ↵ to open · esc to close

Sign in to baba News

Sign in to keep asking. News Plus removes the daily limit.

or use an email code

Ongoing Story· Day 9

Israeli Supreme Court Rules Lenders Must Compensate Buyers for Delayed Apartment Deliveries

3 developments

GlobesPolitics

Supreme Court Rules Lenders May Owe Buyers Compensation for Delays

Translated & summarized from Globes by baba

BusinessNeutral tone

Hebrew · Sole source

Israel's Supreme Court ruled that financial institutions taking over failed construction projects are liable for compensating apartment buyers for delivery delays. The decision, in a Bat Yam case, means lenders may have to cover compensation for delays that occur after they appoint a receiver. This ruling is seen as a significant warning to financing bodies, potentially increasing the cost of rescuing distressed real estate developments.

The story in 5 lines · by baba

  • Financial institutions taking over failed projects are liable for buyer compensation for delivery delays.
  • The Supreme Court ruled lenders may owe compensation for delays occurring after a receiver is appointed.
  • The decision stems from a failed Tama 38/1 project in Bat Yam, Israel.
  • This ruling is considered a significant warning to financing bodies in Israel.
  • Lenders may face increased costs when rescuing distressed real estate developments.

Israel's Supreme Court has ruled that financial institutions that take over failing real estate projects are also responsible for compensating apartment buyers for delivery delays. This landmark decision came in the case of a failed Tama 38/1 project in Bat Yam, where the lending companies had refused to compensate buyers for late delivery.

The case involved a project initiated in 2017, with a commitment to deliver 14 new apartments by the end of 2019. However, the original developer collapsed in 2021, and attorney Hagai Ullman was appointed as the receiver at the request of the financial lenders, including Yesodot Ein Real Estate and Ayalon Insurance Company.

Buyers faced significant delays, with most apartments delivered only last year. One family, who purchased a unit, took the matter to the Tel Aviv District Court seeking compensation for the delay, as stipulated in their contract and the Sale Law. The receiver argued that the lenders' only obligation was through the Sale Law guarantees.

The District Court initially dismissed the family's claim, stating the receiver's appointment was solely for liquidating collateral and that the lenders were not obligated beyond their guarantees. However, the Supreme Court overturned this decision. Justice Ruth Ronen, writing the main opinion, explained that when lenders choose to complete a project, they enter into a 'package deal' and cannot selectively fulfill contractual obligations.

The Supreme Court divided the liability for delays into two parts: those incurred by the original developer and those occurring after the receiver's appointment. Buyers are entitled to compensation from the receiver for the latter period. This ruling serves as a "warning sign for financing bodies," potentially increasing the cost of rescuing failing projects by making lenders liable for ongoing obligations to buyers, including compensation for late deliveries.

GlobesOther · Rishon LeZion

Sign in to baba News

Sign in to follow newsrooms, topics and people.

or use an email code

Sign in to baba News

Sign in to follow newsrooms, topics and people.

or use an email code

Mentioned

Related stories · 2

Not the same event — other stories that share this one’s people, places, or theme: background, reactions, and follow-ups.

Open the Wire