Contractor Must Pay Buyer NIS 134,000 for 21-Month Apartment Delay
The Tel Aviv District Court upheld a NIS 134,188 compensation order against developer Ovi Hakora Megurim for a 21-month delay in delivering a Tel Aviv apartment. The court ruled the occupancy permit was essential for delivery and rejected the developer's appeal, finding the contract's compensation clause invalid.
1 newsroom · 1 language · sincePlus
What happened
- 01Developer Ovi Hakora Megurim ordered to pay buyer NIS 134,188 for 21-month apartment delivery delay.
- 02Tel Aviv District Court rejected developer's appeal, upholding lower court's decision.
- 03Apartment delivery was contingent on obtaining an occupancy permit, which was delayed.
- 04Contractual compensation clause deemed invalid as it was less favorable than the law.
- 05Developer also ordered to pay NIS 15,000 in legal costs and fees.
The developer must also pay NIS 15,000 in legal fees.