Developer Ordered to Pay Monthly Compensation to Buyers for Delayed Apartments

A Herzliya court ordered a developer to pay monthly compensation to nine apartment buyers in Petah Tikva due to a significant delay of 23 to 39 months in delivering their homes. The interim order, considered unusual, mandates payments from October 2026 until delivery.

2 newsrooms · 1 language · since

Sign in to baba News

Sign in to save this article and find it on your phone.

or use an email code

What happened

  1. 01A developer must pay monthly compensation to nine buyers for delayed Petah Tikva apartments.
  2. 02The delay in apartment delivery is between 23 and 39 months past the contract date.
  3. 03The court ordered monthly payments of NIS 6,250 to NIS 7,500 until apartments are delivered.
  4. 04The interim order is considered unique and was granted early in the legal process.
  5. 05A request to force project completion was denied due to the absence of an occupancy permit.
  6. 06The main lawsuit seeking NIS 1.49 million in damages for past delays is still pending.

The court denied a request to force project completion, citing the lack of an occupancy permit. The main lawsuit for NIS 1.49 million in damages is still pending.

Translated and summarized by baba from Ynet, the latest report. Read Ynet’s original

The coverage

2 newsrooms on this story

Who covered it

  • LeftNone
  • Centre1
  • RightNone
  • HarediNone
  • ArabNone
  • Other1

How it broke

See which of the 2 newsrooms broke it, and who waited