Power Outage Highlights Dispute Over New Power Plant Costs

Translated & summarized from Calcalist by baba

BusinessNeutral tone

Hebrew · 1 newsroom

A power outage at the Orot Rabin power station in Hadera has highlighted a dispute between the Israel Electric Corporation (IEC) and the Electricity Authority over NIS 5.35 billion in costs for new power units. The IEC seeks full reimbursement for construction delays, attributing them to force majeure, while the Authority proposes deductions. The incident occurs as the Authority prepares to rule on the IEC's request, amid a broader debate on the IEC's future role in electricity generation.

The story in 6 lines · by baba

  • A power outage at Orot Rabin power station occurred Thursday evening due to a cable short circuit.
  • The incident highlights a dispute over NIS 5.35 billion in costs for new power units at the Hadera facility.
  • The IEC seeks full reimbursement for construction delays, citing force majeure.
  • The Electricity Authority proposed recognizing NIS 5.12 billion, deducting NIS 229 million for delays.
  • A State Comptroller report estimated delays caused NIS 4.6 billion in damages to households.
  • The dispute is linked to a broader debate on the IEC's role in electricity generation.

A widespread power outage affecting central and southern Israel on Thursday evening was caused by a short circuit in cables connecting a new gas turbine at the Orot Rabin power station in Hadera to a substation. While power was quickly restored to homes, the new Unit 80 production unit remained offline for nearly two days. This incident occurs at an awkward time for the Israel Electric Corporation (IEC), as the Electricity Authority is soon to rule on its request to recognize NIS 5.35 billion in costs for building two new production units, 70 and 80, at the Hadera facility. The IEC seeks reimbursement for this investment, including interest, through electricity tariffs.

The malfunction was not in the production unit itself but is linked to a series of costly delays in constructing the new units. Unit 80 was first connected to the grid in January, a year after Unit 70. The original plan was to connect them by June 2022 and March 2023, respectively, meaning their operational delay is about three years. The construction of these combined-cycle units was intended as compensation for the IEC under a sector reform that included privatization of electricity generation, the establishment of the state-owned Noga company to manage the grid, and increased competition.

Delays in the project have been attributed to a chain of failures involving the IEC, regulators, and turbine supplier General Electric, exacerbated by the COVID-19 pandemic and the war following the October 7th attacks. A State Comptroller report estimated that the delays caused NIS 4.6 billion in damages to households, including increased costs from air pollution from older coal units, higher coal expenses, and increased project and financing costs.

The core of the ongoing dispute is the amount of construction costs the state will recognize and reimburse the IEC for via tariffs. The IEC argues all delays were due to force majeure, such as the pandemic and the war. However, the Electricity Authority proposed recognizing NIS 5.12 billion while deducting NIS 229 million for unjustified delays. The IEC claims the Hadera municipality and the Sharon-Carmel Environmental Union delayed permits for Unit 70 for three months over coal pile management, and that General Electric caused over 200 technical issues. The Electricity Authority rejected these claims, deeming them commercial risks that the IEC should pursue with General Electric.

Underlying this is a debate about the IEC's role in electricity generation. The IEC maintains its continued involvement in production is a national security necessity and a factor in keeping tariffs low. Conversely, the Forum of Private Electricity Producers argues the findings support the IEC's exit from generation, stating that in a competitive market, such risks are borne by the entrepreneur, not the public. They fear that unrecognized costs will still be recovered through other tariff components or by impacting grid development.

Keep up with

CalcalistOther · Tel Aviv

Sign in to baba News

Sign in to follow newsrooms, topics and people.

or use an email code

EconomyTopic

Sign in to baba News

Sign in to follow newsrooms, topics and people.

or use an email code

Mentioned

Related stories · 2

Not the same event — other stories that share this one’s people, places, or theme: background, reactions, and follow-ups.

Open the Wire