Bank Leumi Grants Liam Engineering Six-Month Extension on Harish Project Financing

Translated & summarized from Calcalist by baba

BusinessNeutral tone

Hebrew · 1 newsroom

Bank Leumi has extended the deadline for Liam Engineering Group to meet financing conditions for its "Liam Village - Harish Ma'of" project by six months, to May 1, 2027. The company had previously failed to meet the original November 1, 2026 deadline, risking a demand for immediate repayment of NIS 75 million. The extension allows more time to achieve sales targets and settle levies, crucial for securing further credit for the 153-apartment development.

The story in 5 lines · by baba

  • Bank Leumi extended Liam Engineering's financing deadline for the Harish project by six months to May 1, 2027.
  • The company had failed to meet the original November 1, 2026 deadline for project financing conditions.
  • Failure to meet conditions risked immediate repayment of NIS 75 million in credit already provided.
  • Key unmet conditions include apartment pre-sale targets and betterment levy settlements.
  • The project in Harish includes 153 apartments and significant commercial and office space.

Bank Leumi has granted Liam Engineering Group an additional six months to meet the financing conditions for its "Liam Village - Harish Ma'of" project in Harish. The extension pushes the deadline for fulfilling the requirements to open credit lines for the project's second phase from November 1, 2026, to May 1, 2027. This decision follows the company's report last Friday that it had failed to meet the terms of its banking agreement, which had exposed it to the possibility of Bank Leumi demanding immediate repayment of NIS 75 million in credit already provided.

The extension temporarily alleviates the immediate concern of such a demand due to missing the original deadline, but it does not guarantee further credit will be drawn. Key conditions yet to be met include achieving pre-sale targets for apartments and settling betterment levies. The Harish project encompasses 153 apartments, approximately 15,000 square meters of office space, and about 9,000 square meters of retail space.

According to the company's latest financial report, only 17 apartments had been sold by August, though significant marketing for the entire project had not yet commenced. The company estimates that an additional NIS 328 million in investment is required to complete the project. In May 2025, Liam Engineering raised approximately NIS 115 million through its first public bond offering. Prior to the latest report, its bonds were trading at a gross yield to maturity of about 17%, reflecting investor concerns about the associated risks.

The extension provides the company with more time to advance apartment sales and fulfill the necessary conditions for continued banking support, but it does not ensure the opening of credit lines or the project's completion as planned.

CalcalistOther · Tel Aviv

Sign in to baba News

Sign in to follow newsrooms, topics and people.

or use an email code

EconomyTopic

Sign in to baba News

Sign in to follow newsrooms, topics and people.

or use an email code

Mentioned

Related stories · 1

Not the same event — other stories that share this one’s people, places, or theme: background, reactions, and follow-ups.

Open the Wire