Ongoing Story· Day 27

Leviathan Gas Partners Cancel $6.7 Billion Deal with Dalia Energy

5 developments

BizportalEconomy

Dalia Energy Takes New-Med and Ratio to London Arbitration Over $6.7 Billion Gas Deal

Translated & summarized from Bizportal by baba

Business

Hebrew · Sole source

Dalia Energy has filed for international arbitration in London against New-Med Energy and Ratio Oil Exploration regarding a $6.7 billion gas deal for the Leviathan field. Dalia seeks to uphold the agreement after the sellers issued a cancellation notice, citing a dispute over the timeline for regulatory approval. The arbitration is expected to last over a year, but the gas supply is not due to commence until the early 2030s, providing time for a resolution.

The story in 5 lines · by baba

  • Dalia Energy initiated international arbitration in London against New-Med and Ratio over a $6.7 billion gas deal.
  • Dalia seeks to invalidate the sellers' cancellation notice and uphold the gas supply agreement.
  • The dispute centers on the timeline for obtaining regulatory approval for the deal.
  • The gas is intended for two new power plants representing a 10 billion shekel investment.
  • Arbitration is expected to take over a year, but gas supply is not due until the early 2030s.

Dalia Energy, a private electricity company controlled by Eshel Energy, has initiated international arbitration proceedings in London against New-Med Energy and Ratio Oil Exploration over a disputed $6.7 billion gas deal concerning the Leviathan field. Dalia seeks to have the arbitration panel declare the agreement valid and invalidate the sellers' cancellation notice.

The arbitration request outlines three primary demands. First, Dalia wants a declaration that the cancellation notice is invalid and contrary to the agreement or law. Second, even if the cancellation is deemed valid, Dalia argues the agreement remains in effect because regulatory approval from the Antitrust Authority was obtained within the contractually stipulated timeframe. The third demand is a general declaration that the agreement has entered into force according to its terms. Dalia also reserves the right to seek further remedies, potentially including financial compensation, at a later stage.

The dispute stems from a disagreement over the timeline for fulfilling contract contingencies, particularly the Antitrust Authority's approval. The agreement specified a 90-day window for this approval, and the parties differ on when this period began. The Antitrust Authority ultimately granted an exemption from restrictive trade arrangement approval without conditions, except for a clause regarding the legality of secondary gas sales, which was left for the parties to assess. Despite this, New-Med stated it would proceed with the cancellation.

Dalia Energy, which operates a power station providing approximately 8.5% of Israel's electricity, intends to use the gas from Leviathan to fuel two new combined-cycle power plants, each with a capacity of about 850 megawatts. These plants, located in Tzafit and Ashkol in Ashdod, represent an investment of approximately 10 billion shekels, with bank financing already secured. The contract with New-Med and Ratio was crucial, as it was set to supply about 65% of the gas for these new plants, with the remainder coming from Energean's Karish-Tanin fields.

The contract stipulated a binding supply of approximately 1.3 billion cubic meters (BCM) annually, increasing to about 1.7 BCM for roughly 20 years, with prices linked to electricity tariffs. Dalia committed to a minimum take-or-pay quantity. The arbitration is expected to take many months, potentially over a year, but the gas supply is not scheduled to begin until the early 2030s, allowing time for a resolution or settlement before the power plants require the gas.

BizportalOther · Tel Aviv

Sign in to baba News

Sign in to follow newsrooms, topics and people.

or use an email code

EconomyTopic

Sign in to baba News

Sign in to follow newsrooms, topics and people.

or use an email code

Mentioned

Open the Wire