Tel Aviv Begins Demolishing Central Bus Station Bridges After 33 Years
Translated & summarized from Ice by baba
Tel Aviv is set to begin demolishing the bridges of its New Central Bus Station starting January 2027, over 33 years after the station opened. The project, aimed at improving residents' quality of life and correcting past planning errors, will first remove the western bridge. This demolition is timed to avoid disruption to the new Purple Line light rail and is part of a larger plan to reduce activity at the station, which is slated for relocation to Mikveh Israel by 2031-2032.
The story in 5 lines · by baba
- Tel Aviv will start demolishing its New Central Bus Station bridges in January 2027.
- The demolition project aims to improve quality of life and correct past planning mistakes.
- The western bridge will be dismantled first, followed by the northern and southern arms.
- The timing is crucial to avoid disrupting the new Purple Line light rail.
- The Central Bus Station is planned to relocate to Mikveh Israel by 2031-2032.
Tel Aviv-Yafo Municipality has announced the commencement of a project to dismantle the bridges of the New Central Bus Station, a significant change to a prominent transportation landmark in southern Tel Aviv that has stood for over 33 years. The initial phase of demolition is scheduled to begin in January 2027, starting with the western bridge, followed by the northern and southern arms. This initiative aims to transform the area and improve the quality of life for residents in adjacent neighborhoods, as the bridges have become an environmental and planning nuisance due to noise and air pollution.
The timing of the demolition is strategic, taking advantage of a narrow window before the commencement of operations for the Purple Line of the light rail, which runs near the bridges. Delaying the demolition could have resulted in the structures remaining for years or necessitated a prolonged shutdown of the Purple Line in the future.
Tel Aviv Mayor Ron Huldai stated that the demolition of the western bridge represents a correction of a past flawed planning concept that negatively impacted residents' quality of life. He described it as a milestone in the area's rehabilitation and transformation. Huldai added that this is part of a broader municipal plan including a transition to electric buses, dispersal of buses to various terminals, and new planning policies for the bus station complex and its surroundings.
The New Central Bus Station, opened in 1993 after nearly three decades of planning and construction, was once one of the world's largest bus stations. Despite its initial vision of integrating extensive transportation activity with a large commercial center, it struggled to fulfill its potential, with large sections becoming abandoned and businesses closing.
The bridge demolition is part of a larger effort to reduce transportation activity at the site. Under agreements between the municipality and the government, the Central Bus Station is expected to relocate to a replacement complex in Mikveh Israel in about five years. This move will see low-ridership bus lines and bus companies Egged and Dan largely departing from the station. The Mikveh Israel terminal is slated to handle approximately 60% of the current public transportation activity and is expected to open between 2031 and 2032, with a permanent transportation center planned later for Ben Tzvi in Holon.
Demolition of the western bridge is expected to last from January to April 2027, involving cutting, gradual dismantling, and the use of heavy machinery, with temporary traffic disruptions anticipated. Dates for the demolition of the northern and southern arms have not yet been announced. The project is being executed for "Achuzot HaHof" company, with management by Yahel Engineers.