Developer Fined Monthly Sum for Delayed Apartment Delivery
Translated & summarized from Calcalist by baba
A couple in Tel Aviv will receive 30,000 shekels monthly from their developer due to a 20-month delay in apartment delivery. The court ordered the interim payment until the duplex apartment, purchased for 9 million shekels, is officially handed over with an occupancy permit. The buyers cited urgent needs for a safe room during wartime and significant ongoing financing costs. The developer must also pay 10,000 shekels in legal costs.
The story in 5 lines · by baba
- Developer ordered to pay buyers 30,000 shekels monthly for delayed Tel Aviv apartment.
- Couple has waited 20 months past contracted delivery date for their 9 million shekel duplex.
- Court granted temporary financial relief pending resolution of the main lawsuit.
- Buyers cited urgent need for protected apartment during wartime and ongoing financing costs.
- Developer must pay 10,000 shekels in legal costs for the motion.
A couple who purchased a duplex apartment in Tel Aviv for 9 million shekels will receive 30,000 shekels per month from the developer until the apartment is officially delivered. The couple has been waiting 20 months past the contracted delivery date of February 18, 2025, and has paid 8.1 million shekels towards the purchase. The apartment is part of a Tama 38/2 urban renewal project.
The couple, who have joint children, argued they urgently needed a protected apartment with a safe room due to the "Swords of Iron" war and subsequent escalations, forcing them to find temporary housing and incur significant monthly financing costs of approximately 25,000 shekels. They refuse to move into the apartment without a proper occupancy permit (Form 4).
Judge Hagit Bolemash of the Kfar Saba Magistrate's Court granted the couple's request for temporary financial relief, ordering the developer, "Bereshit Hashachar Investments and Properties Dizengoff 27 Tel Aviv," and its controlling owner to pay the monthly sum. This interim payment is separate from the main lawsuit concerning compensation for the past 20 months of delay.
The developer claimed the occupancy permit would be issued within weeks and accused the buyers of delaying the process with complaints and administrative petitions. The judge countered that the developer "holds the stick from both ends," claiming the permit is imminent while the buyers remain unable to occupy their property.
The court mandated the interim payments retroactively from the date the request was filed (October 20, 2026) until the apartment is legally delivered and an occupancy permit is obtained. The developer was also ordered to pay 10,000 shekels in legal costs for the motion. The ruling stated that if the developer presents evidence of lower market rental values, the monthly sum could be reduced.