Mega Or Signs New Data Center Deal With Nebius, Boosting Annual Revenue
Translated & summarized from Calcalist by baba
Mega Or has signed a new deal with Nebius to provide 134 megawatts of IT capacity across two data centers in Beit Shemesh and Masmiya. The company expects this agreement to generate NIS 550 million in annual NOI, adding to its existing data center revenue projections. This is the third deal between Mega DC and Nebius, a major cloud and AI infrastructure provider. Mega Or anticipates completing the facilities by mid-2028, with construction costs estimated at $1.6 billion.
The story in 5 lines · by baba
- Mega Or will supply 134 MW IT to Nebius across two new data centers in Beit Shemesh and Masmiya.
- The new deal is expected to generate NIS 550 million in annual Net Operating Income for Mega Or.
- This agreement is Mega DC's third with Nebius, a Nasdaq-listed cloud and AI infrastructure company.
- Mega Or estimates the construction cost for the two facilities at approximately $1.6 billion.
- The company expects to complete the data centers by the second quarter of 2028.
Real estate company Mega Or has entered into a new agreement with Nebius to supply 134 megawatts of IT capacity across two data centers. One facility is under construction in Beit Shemesh, and the second will be built in Masmiya (Yoav Regional Council). Mega Or estimates that the average annual Net Operating Income (NOI) from these centers, once fully occupied, will reach NIS 550 million. This new income stream is in addition to the NIS 740 million in annual NOI Mega Or anticipates from previously signed data center contracts.
This marks the third agreement between Mega DC, Mega Or's subsidiary for data center operations, and Nebius, a cloud and AI infrastructure company listed on Nasdaq with a market capitalization of $31 billion. Previous deals include one from January for 80 megawatts IT across facilities in Beit Shemesh and Masmiya, and another from May of the previous year for 8 megawatts IT from a Modi'in facility. The combined expected annual NOI from these prior agreements is estimated at NIS 335 million.
The new agreement's Beit Shemesh facility, MDCIL-4, is already under construction and has a power connection permit, with a maximum capacity of 135 megawatts IT. The current deal covers half of this capacity, representing the second phase of the campus. The first phase, with 58 megawatts IT, will serve Nebius under the January agreement and is expected to be ready for customization in the current quarter.
The Masmiya facility, MDCIL-7, is designated for future development, and Mega Or is awaiting a power connection permit, which is a condition for finalizing the deal with Nebius. The Israel Electric Corporation's regulatory body has paused the processing of this permit request. Mega Or projects the completion of both facilities by the end of the second quarter of 2028, with a seven-year service period for Nebius, including an option for a five-year extension.
Mega Or estimates the construction cost for these facilities at approximately $1.6 billion, or $12 million per megawatt IT. The company, valued at NIS 16.8 billion, is the fourth-largest by market cap in the TA Yielding Israel index and the only one among the top 10 to show positive stock returns this year, with a 64% increase attributed to investor enthusiasm for its data center growth. The company's stock saw unusually high trading volume the day before the announcement.