Abu Homes to Receive Up to 33 Million Shekels Compensation for Ashdod Project Delay
Translated & summarized from Ice by baba
Real estate developer Tzachi Abu's company, Abu Homes, will receive up to 33.2 million shekels in compensation due to a delay in the handover of 198 apartments in the "Family Towers" project in Ashdod until January 2029. The compensation is structured as two annual payments of up to 16.6 million shekels each. The deal also includes a revised payment schedule for the remaining transaction balance. In related news, Abu recently acquired 50 units in Netanya, and Tzachi Abu is set to resume his role as Chairman of Waybox.
The story in 6 lines · by baba
- Abu Homes will receive up to 33.2 million shekels compensation for a delayed Ashdod apartment project.
- The "Family Towers" project in Ashdod will see apartment handovers delayed until January 2029.
- Compensation will be paid in two annual installments of up to 16.6 million shekels each.
- Abu Homes also restructured payments for the remaining 146 million shekel balance of the deal.
- Tzachi Abu recently acquired 50 units in Netanya for 120 million shekels.
- Gadi Ben Haim was appointed CEO of Waybox, with Tzachi Abu returning as Chairman.
Real estate company Abu Homes has signed an updated addendum to its agreement to purchase the "Family Towers" project in Ashdod. The deal includes a significant delay in the handover of 198 apartments until January 2029, for which Abu Homes will receive compensation. The seller has committed to paying Abu Homes an annual compensation of up to 33.2 million shekels spread over two years, contingent on the occupancy delay. This compensation is divided into two equal annual installments, with up to approximately 16.6 million shekels for the first year (January 2027 to January 2028) and another up to 16.6 million shekels for the second year (until January 2029). The compensation will be calculated proportionally for each apartment until its actual delivery, and the seller's obligations are secured by appropriate guarantees.
In parallel with the delivery delay, the parties have also restructured the payment schedule for the remaining balance of the transaction, which amounts to 146 million shekels (before VAT and indexation). The fourth payment, originally set at about 74.7 million shekels, has been split: 35 million shekels will be transferred within a week of the addendum's signing, with the remaining approximately 39.7 million shekels due by January 26, 2027, plus indexation. On the same date, January 26, 2027, Abu Homes is expected to make the fifth and final payment of about 71.3 million shekels, plus VAT and indexation.
As part of the new understandings, 7.8 million shekels will be deducted from the indexation differences applicable to payments to the seller, benefiting Abu Homes. Separately, Tzachi Abu recently completed the acquisition of 50 housing units in the "N Weizmann" project in Netanya from Azorim for approximately 120 million shekels (including VAT). These units are designated for Waybox's long-term rental housing system, with Abu purchasing them at about 15% below market price.
Additionally, the board of directors of urban renewal company Waybox approved the appointment of Gadi Ben Haim as CEO. Tzachi Abu is expected to return to his role as Chairman of the company, having previously served as interim CEO.