Get Plus

Sign in to baba News

One account across the web, iPhone and Android — your subscription follows it.

or use an email code

Search stories

Type at least two characters. Results come from every newsroom baba reads.

↑↓ to move · ↵ to open · esc to close

Sign in to baba News

Sign in to keep asking. News Plus removes the daily limit.

or use an email code

CalcalistEconomy

Azrieli Data Centers Expect No Major Impact From Norway's Connection Freeze

Translated & summarized from Calcalist by baba

BusinessNeutral tone

Hebrew · 1 newsroom

Azrieli Group's data center operations in Norway will not be significantly impacted by a temporary freeze on new electricity connections for data centers, according to the company. The Norwegian grid operator's decision, which mirrors a similar move by Israeli regulators, is in place until August 1, 2027, to develop updated grid policies. Azrieli's new 80-megawatt data center, financed by a 1.4 billion euro agreement, is expected to begin operations in July 2027, only slightly delayed.

The story in 5 lines · by baba

  • Norway's electricity grid operator has temporarily frozen new data center connections until August 2027.
  • Azrieli Group expects no significant impact on its Norwegian data center operations.
  • A similar decision was also made by the Israeli regulator.
  • Azrieli's new 80 MW data center is financed by a 1.4 billion euro agreement.
  • The new data center's operational start is delayed to July 2027.

Azrieli Group's data center operations in Norway are facing a new challenge as the country's electricity grid operator has decided to temporarily freeze new electricity capacity allocations for connecting data centers. The freeze will halt processing of applications for new facilities and for increasing power supply to existing ones, pending the development of an updated policy to ensure grid safety and stability. This suspension is expected to last until August 1, 2027, at the latest. A similar decision was also made by the Israeli regulator.

Azrieli clarified in a stock exchange report that, based on an initial assessment, this decision is not anticipated to significantly affect its data center operations in Norway or its ongoing projects, including the new data center being built by its subsidiary, Green Mountain. In October, Azrieli announced that Green Mountain secured a 1.4 billion euro financing agreement for this new data center. At that time, the company also reported a 16-week delay in its schedule, pushing the operational start from late March 2027 to July 2027. Consequently, the current freeze on approvals until August 2027 is unlikely to substantially delay the site's commencement of operations.

The new data center will have a capacity of 80 megawatts, joining an existing 90-megawatt facility that is already operational and serving TikTok. Azrieli also operates smaller data centers in Germany and the United Kingdom.

CalcalistOther · Tel Aviv

Sign in to baba News

Sign in to follow newsrooms, topics and people.

or use an email code

EconomyTopic

Sign in to baba News

Sign in to follow newsrooms, topics and people.

or use an email code

Mentioned

Open the Wire