Tiberias Central Bus Station Project Delayed Until 2027 Due to Unexpected Foundation Issues

Translated & summarized from Maariv by baba

CenterCharged tone

Hebrew · 1 newsroom

The new central bus station in Tiberias, Israel, originally slated for completion in 2026, has been postponed until late 2027. Unexpected structural issues with the old building's foundations required a complete demolition and rebuild, compounded by delays from the security situation. Passengers are currently using inadequate temporary facilities, prompting the Ministry of Transportation to improve conditions while construction continues.

The story in 5 lines · by baba

  • Tiberias' new central bus station project is delayed until the 2027 holiday season.
  • Unexpected foundation instability required demolition and a complete rebuild of the station.
  • The security situation and war in the north have also contributed to construction delays.
  • Passengers are enduring harsh weather in temporary, inadequate waiting areas.
  • The Ministry of Transportation is working to improve temporary facilities and expedite the project.

The construction of a new central bus station in Tiberias, northern Israel, has been significantly delayed and is now expected to be completed by the holiday season of 2027, more than a year after its initially planned opening. Passengers are currently enduring harsh weather conditions in temporary facilities, with complaints about the inadequate waiting areas.

The project, initially envisioned as a renovation, was unexpectedly halted when construction revealed that the existing building's foundations were unstable, necessitating a complete demolition and a new construction from scratch. The Ministry of Transportation stated that this decision was primarily driven by safety concerns. Further delays were attributed to the security situation and the war's impact on northern Israel, leading to a revised completion date.

Passengers who were promised a modern, air-conditioned facility with 13 accessible platforms and amenities by 2026 are now facing another summer and winter in temporary outdoor shelters. These temporary sites feature basic wooden benches under metal roofing, open bus plazas, and are marked by construction fences, with cracked walkways and worn road markings.

In response to passenger complaints, the Ministry of Transportation and the National Public Transport Authority are working to improve the temporary waiting areas. Efforts include adding roofing to a temporary terminal, installing additional benches, and ensuring safer passage. The ministry has assured the public that they are closely monitoring the project and collaborating with the developer to minimize inconvenience until the new station, which promises a significant upgrade, is finished.

MaarivCentre · Jerusalem

Sign in to baba News

Sign in to follow newsrooms, topics and people.

or use an email code

EconomyTopic

Sign in to baba News

Sign in to follow newsrooms, topics and people.

or use an email code

Mentioned

Related stories · 1

Not the same event — other stories that share this one’s people, places, or theme: background, reactions, and follow-ups.

Open the Wire