Azrieli Group Secures Over €1 Billion in Financing for Norwegian Data Center Campus

Translated & summarized from 0404 by baba

RightNeutral tone

Hebrew · 2 newsrooms covering

Azrieli Group's Norwegian subsidiary has secured over €1 billion in financing for an 80-megawatt data center campus. The deal includes a €1.007 billion credit line for construction and allows Azrieli to recoup €260 million in invested equity. The project, built for an international tech firm, will see its first delivery delayed to July 2027 due to client-requested specification changes. These changes will postpone the start of revenue generation from the campus.

The story in 6 lines · by baba

  • Azrieli Group secured over €1 billion in financing for a Norwegian data center campus.
  • The financing package includes a €1.007 billion credit line for construction.
  • Azrieli expects to recoup €260 million in previously invested equity.
  • The campus is being built for an international technology company.
  • Project delivery is delayed to July 2027 due to client specification changes.
  • Revenue generation from the campus will be postponed due to these changes.

Azrieli Group announced Thursday to the Tel Aviv Stock Exchange that its Norwegian subsidiary has finalized a significant financing agreement for the construction of a 80-megawatt data center campus. The agreement, signed Wednesday between Green Mountain Undheim Investment, a wholly-owned subsidiary of Azrieli's data center arm, and a foreign banking consortium, includes a credit line of up to €1.007 billion for the project's development. Additional credit facilities include up to €25 million for ongoing operations, €165 million for customer reimbursements, and approximately €103 million for VAT payments. The total package could reach up to €1.3 billion, with an option for a further €100 million expansion subject to bank approval.

Under the terms, Azrieli can finance up to 85% of recognized construction costs through debt, with funds disbursed as work progresses. Upon meeting the conditions for the initial withdrawal, Azrieli expects to recoup approximately €260 million in excess equity already invested. The interest rate is variable, set at Euribor plus a 2% to 3% margin annually, with the construction facility valid for up to seven years. Azrieli will provide guarantees for cost overruns and an unlimited guarantee for project completion, while maintaining a minimum credit rating of BBB-.

The campus is being built for an international technology company that signed a 15-year service agreement with Azrieli in December 2025. Azrieli initially projected the fully operational campus to generate an average net operating income (NOI) of around €117 million annually. This financing deal follows Azrieli's recent update that the client requested specification changes, leading to a delay in the delivery of the first 20 megawatts from March to July 2027, with the second phase also postponed by about three months. These mutually agreed-upon changes will postpone the start of revenue generation from the campus.

0404Right · Jerusalem

Sign in to baba News

Sign in to follow newsrooms, topics and people.

or use an email code

EconomyTopic

Sign in to baba News

Sign in to follow newsrooms, topics and people.

or use an email code

Mentioned

Full coverage · 2 outlets
First: Bizportal · 6h ago

The same event, reported separately by each outlet. Open a few to compare what different newsrooms emphasize — and what they leave out.

Open the Wire